Significant progress has been made on a new Sebastian County EMS facility that is coming to Greenwood.

Sebastian County Judge David Hudson said Tuesday the architect for the project, Studio 6 Architects, projects construction is 55 percent complete at this time, and the project is on schedule for the contracted completion date of June 28.

Much of the facility is currently in the dry to allow construction to proceed in bad weather, Hudson said. Garage doors, windows and doors are being installed, and sheetrock is beginning to be installed for interior walls.